Jan 4, 2019

Trails in Vayots Dzor Region: maintenance and signposting (TECHNICAL REPORT)

HIKEArmenia and Trails for Change Donation Contract 01․04․2019

Maintenance and signposting of hiking trails on segments

Gomk -Martiros, Old Martiros Loop, Kapuyt Loop Trail, Artavan Loop Trail


Technical report is to specify the work done by “Trails for Change” Tourism Infrastructure Development NGO in the period from 04.09.2019 to 18.09.2019 in the frame of HIKEArmenia and Trails for Change Donation contract (date: 01.04.2019). Intended work for this period was: 8 km of trail blazing, signposting, trail building, bush clearing of Gomk Martiros Trail, 6,5 km of signposting of Old Martiros Loop, 16 km of trail blazing of Artavan Loop, 13,6 km of signposting of Kapuyt Loop Trail.

The report will show the completed work.COMPLETED WORKS

Gomk Martiros Trail

Old Martiros Loop

Kapuyt Loop Trail

Artavan Loop Trail

Prepared by “Trails for Change” Tourism Infrastructure Development NGO, on 16.10.2019 for HA Foundation


Anna Tadevosyan: TFC General Manager

Ashot Davtyan: TFC Project Manager

Aida Arakelyan: TFC Project Manager Assistant

Armen Manukyan: TFC Trail Crew Lead