HIKEArmenia and Trails for Change Donation Contract 01․04․2019
Maintenance and signposting of hiking trails on segments
Gomk -Martiros, Old Martiros Loop, Kapuyt Loop Trail, Artavan Loop Trail

Technical report is to specify the work done by “Trails for Change” Tourism Infrastructure Development NGO in the period from 04.09.2019 to 18.09.2019 in the frame of HIKEArmenia and Trails for Change Donation contract (date: 01.04.2019). Intended work for this period was: 8 km of trail blazing, signposting, trail building, bush clearing of Gomk Martiros Trail, 6,5 km of signposting of Old Martiros Loop, 16 km of trail blazing of Artavan Loop, 13,6 km of signposting of Kapuyt Loop Trail.
The report will show the completed work.COMPLETED WORKS
Gomk Martiros Trail


Old Martiros Loop


Kapuyt Loop Trail


Artavan Loop Trail


Prepared by “Trails for Change” Tourism Infrastructure Development NGO, on 16.10.2019 for HA Foundation
Anna Tadevosyan: TFC General Manager
Ashot Davtyan: TFC Project Manager
Aida Arakelyan: TFC Project Manager Assistant
Armen Manukyan: TFC Trail Crew Lead